• View enhanced case on Westlaw
  • KeyCite this case on Westlaw
  • http://laws.findlaw.com/7th/011380.html
    USA v. ALSHABKHOUN, SHAKEAB
    
    In the
    United States Court of Appeals
    For the Seventh Circuit
    
    No. 01-1380
    
    United States of America,
    
    Plaintiff-Appellee,
    
    v.
    
    Shakeab Alshabkhoun and A&A Farms,
    
    Defendants-Appellants.
    
    Appeal from the United States District Court
    for the Western District of Wisconsin.
    No. 98-C-583-S--John C. Shabaz, Judge.
    
    Argued October 31, 2001--Decided January 18, 2002
    
    
      Before Bauer, Coffey and Diane P. Wood,
    Circuit Judges.
    
      Bauer, Circuit Judge.  The United States
    and appellants Shakeab Alshabkhoun and
    A&A Farms (collectively A&A) entered into
    a court-approved Consent Decree to
    resolve the government's claims that A&A
    violated the Clean Water Act. When A&A
    failed to comply with the terms of the
    Consent Decree, the government moved to
    enforce the stipulated penalties
    provision. The district court granted the
    government's motion and ordered A&A to
    pay stipulated penalties and attorney's
    fees. A&A appealed that ruling. For the
    reasons set forth below, we affirm the
    district court.
    
    I.  Background
    
      A&A owns 1,000 acres of farmland
    adjacent to the Wisconsin River in Dane
    County, Wisconsin. In January of 1994,
    A&A excavated a drainage ditch system to
    collect water and excess soil from the
    farm and neighboring land and convey it
    to the river. The system required a ditch
    that was 38 feet wide and 1,500 feet
    long, which resulted in the discharge of
    dredged or fill materials into the
    wetlands. A&A did not obtain a permit
    from the United States to construct this
    drainage ditch system.
    
      On December 4, 1996, the Environmental
    Protection Agency (EPA) issued an
    administrative compliance order stating
    that A&A's construction of the ditch
    without a permit was a violation of the
    Clean Water Act. The Clean Water Act
    prohibits the discharge of any pollutant,
    including dredged or fill material, into
    navigable waters of the United States,
    except in accordance with a permit. 33
    U.S.C. sec. 1311(a). A&A then submitted a
    restoration plan that the EPA rejected
    and further attempts to resolve the
    dispute failed.
    
      On August 13, 1998, the United States
    filed a civil action in federal district
    court under section 309 of the Clean
    Water Act. The court entered partial
    summary judgment in favor of the
    government and, on July 2, 1999, the
    parties entered into a Consent Decree for
    the restoration of the wetlands. The
    decree was negotiated by both parties and
    approved by the district court. It
    required A&A to pay $225,000 in civil
    penalties. Further, to properly restore
    the wetlands, the Consent Decree required
    A&A to submit to the EPA a Restoration
    Work Plan, prepared by a certified
    engineer, and a schedule for completing
    the tasks set forth in the Plan.
    
      The Consent Decree provided for
    stipulated penalties for any failure to
    implement the Plan in compliance with the
    schedule. Specifically, the Consent
    Decree required the payment of $500 per
    day for one to thirty days of
    noncompliance, $1,000 per day for thirty-
    one to sixty days of noncompliance and
    $2,000 per day for sixty-one or more days
    of noncompliance. The Consent Decree
    allowed for the extension of the
    deadlines if "performance is prevented or
    delayed solely by events which constitute
    a Force Majeure event," defined to
    exclude "normal precipitation or climate
    events." A&A was required to notify the
    government in writing of any alleged
    Force Majeure event to invoke the
    extension of deadlines.
    
      The Consent Decree also included a
    dispute resolution provision. Under this
    provision, if A&A filed a petition in
    court concerning the Consent Decree,
    A&A's penalties would continue to accrue
    during the proceedings; however, the
    filing of a petition would stay A&A's
    obligation to pay any penalty regarding
    the disputed matter. In the event that
    A&A did not prevail on the matter in
    dispute, the stipulated penalties became
    due.
    
      The Plan required A&A to obtain bids
    from contractors within thirty days of
    the approval of the Plan, complete
    grading and installation of erosion
    control measures within forty-five days
    thereafter, and plant the required trees,
    shrubs and seeds within thirty days after
    that. A&A hired a contractor and began
    the work in late November of 1999, but
    did not complete the project. More than
    two months later, on February 17, 2000,
    A&A filed a notice of dispute with the
    EPA, requesting relief from the Plan on
    the grounds that compliance was
    impossible. A&A stated that it had hired
    additional experts who opined that the
    implementation of the Plan could
    potentially cause flooding problems. The
    EPA reviewed this information and denied
    A&A relief.
    
      On April 7, 2000, invoking the decree's
    dispute resolution clause, A&A filed a
    Petition to Modify the Consent Decree
    with the district court claiming that
    significant unforeseen circumstances
    affected its ability to perform the work.
    The court rejected A&A's impossibility
    claim and instead found that since the
    drainage problem was the very reason A&A
    constructed the ditch at issue, A&A was
    well aware of its experts' observations
    and the potential for drainage problems
    at the time the Consent Decree was
    negotiated. As a result, on May 26, 2000,
    the district court held that A&A had
    failed to present adequate grounds for
    any modification of the decree and the
    petition was denied.
    
      In June of 2000, spring flooding
    rendered the land unsuitable for work.
    A&A did complete the required excavation
    in October of 2000, but the parties were
    still in dispute over the issue of
    stipulated penalties for the delay. On
    October 23, 2000, the government filed a
    Petition to Enforce the Consent Decree,
    asking the court for an award of
    $507,850.40. The amount represented the
    accumulation of the stipulated daily
    penalties, as well as attorney's fees. In
    response, A&A did not contest the
    calculation of damages, but argued that
    the stipulated penalties provision was
    unreasonable and unenforceable and that
    the delay in completing the work should
    be excused due to the June flooding.
    
      On January 11, 2001, the district court
    granted the government's petition in
    full. The court held that the stipulated
    penalty provision was reasonable and
    enforceable because it amounted to less
    than 10% of the penalty authorized by
    statute. Further, the court refused to
    excuse the delay due to the June flooding
    because had A&A implemented the Plan in a
    timely manner seven months earlier, the
    June flooding would have been irrelevant.
    A&A then brought this appeal.
    
    II.  Discussion
    
      Because a consent decree is a form of
    contract, we generally review a district
    court's interpretation of the consent
    decree de novo. Goluba v. Sch. Dist. of
    Ripon, 45 F.3d 1035, 1037-38 (7th Cir.
    1995). However, where, as here, the
    district court oversaw and approved the
    consent decree, we give "some deference"
    to the district court's interpretation.
    Id.
    
      A&A concedes that the construction of
    the ditch violated the Clean Water Act.
    The sole issue raised on this appeal is
    whether the district court's enforcement
    of the Consent Decree is against public
    policy. A&A presents two arguments: (1)
    that the stipulated penalty provision in
    the Consent Decree is void and
    unenforceable as a matter of public
    policy because it allows for penalties to
    accrue while the parties engage in the
    dispute resolution process; and (2) that
    the district court erred in penalizing
    A&A for the delay in compliance with the
    schedule because it was unable to perform
    the work due to the June flooding. We
    find both arguments to be without merit.
    
      A consent decree is a court order that
    embodies the terms agreed upon by the
    parties as a compromise to litigation.
    United States v. Witco Corp., 76 F. Supp.
    2d 519, 525 (D. Del. 1999). For purposes
    of construction, a judicially approved
    consent decree is essentially a contract.
    United States v. City of Northlake,
    Illinois, 942 F.2d 1164, 1167 (7th Cir.
    1991). While a consent decree is also
    deemed a judgment of the court, "it is
    the parties' agreement that serves as the
    source of the court's authority to enter
    any judgment at all." Local 93, Int'l
    Ass'n of Firefighters v. City of
    Cleveland, 478 U.S. 501, 522 (1986); King
    v. Walters, 190 F.3d 784 (7th Cir. 1999).
    
      A provision within a consent decree
    fixing a stipulated penalty is
    unenforceable if it constitutes an
    unreasonable penalty or is void as a
    matter of public policy. South Suburban
    Hous. Ctr. v. Berry, 186 F.3d 851, 856
    (7th Cir. 1999). A&A argues that the
    stipulated penalty provision in the
    Consent Decree forces A&A to effectively
    surrender its rights to invoke the
    dispute resolution process because
    stipulated penalties might be imposed
    while the dispute is pending. In support
    of its public policy argument, A&A relies
    heavily on United States v. Witco
    Corporation, in which a United States
    District Court rendered a similar
    stipulated penalty provision void and
    unenforceable.
    
      In Witco, the EPA asserted a claim
    against Witco Corporation, a property
    owner, seeking the clean-up of a contami
    nated land site. Witco Corp., 76 F. Supp.
    2d at 521. Witco and the EPA entered into
    a consent decree that provided for
    stipulated penalties if Witco failed to
    comply with the decree's terms and the
    accrual of penalties during any period of
    dispute resolution. Id. at 522-23. Witco
    invoked the dispute resolution clause but
    did not succeed in the dispute. The EPA
    sought collection of the stipulated
    penalties, including those that had
    accrued during the dispute. Id. at 524.
    The district court refused to award such
    penalties. Id. at 531. Reasoning that
    enforcement of the stipulated penalties
    provision would penalize Witco for
    asserting its rights to judicial process,
    the court determined that the stipulated
    penalty provision was against public
    policy and therefore, unenforceable
    because it allowed penalties to accrue
    while the dispute was pending. Id. at
    529-30.
    
      A&A's reliance on Witco is misplaced.
    The decisions of the district court of
    Delaware are not controlling authority in
    this jurisdiction and Witco is notably
    distinguishable from A&A's case. First,
    Witco completed the required clean-up
    before invoking the dispute resolution
    clause. Id. at 523. The penalties at
    issue in that case accrued only while the
    dispute over fee amounts was pending, and
    Witco's dispute involved a change in the
    law since the entry of the consent
    decree. Unlike the instant case, Witco
    had fully remedied the environmental harm
    by completing its work, and the accrued
    penalties at issue were unrelated to any
    continuing environmental violation. Id.
    at 530-31.
    
      In contrast, A&A invoked the dispute
    resolution procedures while the required
    work was still uncompleted. A&A's
    penalties accrued during this period not
    because of a late payment, but because of
    the unwarranted delay in completing the
    restoration of the wetlands, as required
    by the Consent Decree. In addition, while
    Witco brought a good faith claim based on
    a change in the law, A&A sought to modify
    the decree here without any similar,
    legitimate basis. We agree with the
    district court that Witco was not
    instructive in this case.
    
      More analogous is United States v.
    Krilich, 126 F.3d 1035 (7th Cir. 1997),
    in which we upheld the imposition of over
    $1 million in stipulated penalties.
    Krilich, a property owner, entered into a
    consent decree to settle the government's
    Clean Water Act claims. Krilich, 126 F.3d
    at 1036. In the decree, Krilich promised
    to restore the subject wetlands according
    to a schedule. Krilich missed the
    scheduled deadlines and the government
    moved to enforce the decree's stipulated
    penalties provision. Id. The district
    court granted the motion and we affirmed.
    In so doing, we noted that Krilich had
    negotiated the decree, entered into it
    freely, and never properly modified any
    of the deadlines. Id. at 1037.
    Accordingly, Krilich was bound to pay the
    stipulated penalties set forth in the
    consent decree. We believe that the
    result in Krilich is warranted in the
    instant case.
    
      We agree with A&A that access to the
    courts is of paramount importance.
    However, it does not follow that an
    agreed upon provision that allows for the
    accrual of stipulated penalties during
    any dispute resolution is unenforceable
    as a matter of public policy. It is
    undisputed that this Consent Decree was
    drafted and negotiated by both parties
    and entered into voluntarily. A&A cannot
    now escape the consequences of the
    Consent Decree with a public policy
    argument that the provision inhibits its
    right to access the courts. A&A's blanket
    statement that the "right to dispute
    resolution 'rings hollow' when
    accompanied by the risk of penalties" is
    overbroad. In fact, the stipulated
    penalty accrual provision does not apply
    to a successful claim. Unfortunately for
    A&A, it was not successful on its
    petition to modify the Consent Decree. As
    a result, A&A is liable for the penalties
    that accrued during the resolution of
    that dispute. To excuse A&A from the
    stipulated penalties would undermine the
    clear terms of the Consent Decree
    andprovide any party to a Consent Decree
    with a method of delaying performance by
    invoking the dispute resolution clause
    with meritless claims.
    
      Although unreasonable penalties may well
    be unenforceable, we believe the
    stipulated penalties imposed under this
    Consent Decree are reasonable under these
    circumstances. See, e.g., United States
    v. Krilich, 948 F. Supp. 719, 726 (N.D.
    Ill. 1996). The penalties are directly
    related to the environmental harm caused
    by A&A. Further, the amount is less than
    10% of the statutory authorized
    penalties. See 33 U.S.C. sec. 1319(d).
    
      A&A also argues that the stipulated
    penalties were unreasonable as a matter
    of public policy since the delay in work
    was attributable to weather conditions
    beyond its control. It argues that it did
    not resume work following the resolution
    of the dispute because June flooding
    rendered the land unsuitable for work.
    A&A adds that even the government
    concedes that the land was too wet for
    the work at the time. The Consent Decree
    provided that a deadline may be excused
    in the event of a "Force Majeure." This
    provision, however, required A&A to
    notify the government in writing of the
    alleged Force Majeure event in order to
    excuse a deadline. Because A&A failed to
    do so, A&A cannot now claim that
    compliance with the schedule was not pos
    sible. See, e.g., Krilich, 126 F.2d at
    1037. Moreover, because June was a full
    seven months after the Consent Decree's
    deadlines for completing the work, any
    flooding in June does not warrant an
    excuse for the delay and is therefore ir
    relevant to the issue of stipulated
    penalties.
    
    III.  Conclusion
    
      For the foregoing reasons, we AFFIRM the
    judgment of the district court.
    

    FindLaw Career Center

      Search for Law Jobs:

        Post a Job  |  View More Jobs
    Ads by FindLaw