Laws: Cases and Codes : U.S. Code : Title 42 : Section 1962d-5


   
U.S. Code as of: 01/19/04
Section 1962d-5. Water resources development projects involving navigation, flood control, and shore protection

    (a) Construction, operation, and maintenance; limitation on
      estimated Federal first cost of construction; Congressional
      committee approval of projects; reports to Congress
      The Secretary of the Army, acting through the Chief of Engineers,
    is authorized to construct, operate, and maintain any water
    resource development project, including single and multiple purpose
    projects involving, but not limited to, navigation, flood control,
    and shore protection, if the estimated Federal first cost of
    constructing such project is less than $15,000,000. No
    appropriation shall be made to construct, operate, or maintain any
    such project if such project has not been approved by resolutions
    adopted by the Committee on Environment and Public Works of the
    Senate and the Committee on Public Works and Transportation of the
    House of Representatives, respectively. For the purpose of securing
    consideration of such approval the Secretary shall transmit to
    Congress a report of such proposed project, including all relevant
    data and all costs.
    (b) Local cooperation requirements based on certain estimated
      Federal first cost of construction
      Any water resource development project authorized to be
    constructed by this section shall be subject to the same
    requirements of local cooperation as it would be if the estimated
    Federal first cost of such project were $15,000,000 or more.



Previous [Notes] Next

Related Resources

Health Law Guide

Health Articles and Documents

Health Discussion

FindLaw Career Center

    Search for Law Jobs:

      Post a Job  |  View More Jobs
Ads by FindLaw