|
|
|
U.S. Code as of:
01/19/04
Section 2331. Use of continuing contracts for construction of certain projects
(a) In general
Notwithstanding any other provision of law, the Secretary shall
not implement a fully allocated funding policy with respect to a
water resource project if initiation of construction has occurred
but sufficient funds are not available to complete the project.
(b) Continuing contracts
The Secretary shall enter into a continuing contract for a
project described in subsection (a) of this section.
(c) Initiation of construction clarified
For the purposes of this section, initiation of construction for
a project occurs on the date of enactment of an Act that
appropriates funds for the project from 1 of the following
appropriation accounts:
(1) Construction, General.
(2) Operation and Maintenance, General.
(3) Flood Control, Mississippi River and Tributaries.
|
|